Need to run power to the pole shed, and I need to tie in to this mess.



Call the utility location service- check
rent a trencher, order and install ~ 320 ft underground cable to correct depth- check
order and install panel, breakers, EMT and lighting in shed-check
install outlets, run all conductors-check
tie in to this load center in the house-hmmmm
need to investigate this a bit more, and hopefully not have to do another drop and run from the road.